NEW CONSTRUCTION, ADDITIONS AND RENOVATIONS
Red Hook Central Schools, Red Hook, NY
This project involved the Mill Road Elementary School, Linden Avenue
Middle School and the Red Hook High School.
A 33,000 SF addition and a
25,000 SF renovation were conducted at Linden Avenue Middle School. The new
gymnasium, nine new classrooms, 11,000 SF six-bay bus garage addition and
storage faciliies will help the district continue to meet the needs of a steadily
increasing student body (2,200+) and dedicated teaching staff of more than
300.
The high school building improvements included a 22,000 SF addition and
6,000 SF in renovation construction (exterior and interior). The scope of
work included ten new classrooms, a four station gymnasium, conversion of a
gym/auditorium to an auditorium/large group instructional area, a new pupil
personnel office, a running track, and six new playing fields.
|